Splitting a block of multiple time slots

Splitting a block of time slots allows the group planner to add assignments one time slot at a time in a situation where a resource is not available for the entire block of time slots.

 

From the Schedule Tool:

    1. Got to the Tasks tab
    2. Click on the block to divide
    3. Select the Split option on the menu on the right
    4. Apply the changes.
    5. Go back to the Plan tab to assign the shift individually. 

mceclip3.png

 

The following icons in the individual day cells indicate that the block will be split once the changes are saved: